Project: Overhaul the coal conveyor weighing system at Duyen Hai thermal power plant
Year of implementation: 2023
Scope of work: Remove, repair and move 2 pounds of coal at conveyor belts BC1A/B wharf 1 installed for conveyor lines BC1’/”B transporting coal to coal storage of Duyen Hai 1 thermal power plant.
– Remove, repair and move 2 pounds of coal at the BC1A/B conveyor belts at wharf 2 installed for the BC2A/B conveyor lines transporting coal to the coal storage of Duyen Hai 3MR thermal power plant.