Project: Upgrading the soft start system with an inverter for cooling fans – Cam Pha Cement Factory
Completion time: October 2014
Content: Redesign the electrical system to replace 9 soft start cabinets with 9 inverter cabinets used to control clinker cooling fans at Cam Pha cement factory.
The original soft starter cabinet
Inverter cabinets after replacement