Power and control system for Screening-Separation cluster for Lep My coal screening plant

Project name: Supply and installation of power and control system for Screening-Separation cluster for Lep My coal screening plant

Implementation time: 2018

Design, supply and operate Screening and Separation systems including:

  • Operation station at the control house of 1.5 million tons/year screen cluster (Floor +21)
  • Control cabinet DK 2 at the 1.5 million tons/year screen cluster
  • Control cabinet DK 3 at the conveyor control house B800x380m, floor +21
  • Control station and data collection of RTU01 conveyor at the conveyor control house B1000x915m, floor +30.
  • Siemens controller: S7-300, S7-1200.
  • Communication connection standard: Profinet.
  • Monitoring and control interface WinCC V14 Professional–SP1.