Hai Anh wind power plant synchronizes with national grid

Hai Anh Wind Power Plant in Quang Tri officially synchronized with the National Power Grid on June 30, 2025. This is a crucial step, preparing the plant for  commercial operation by August 2025.

The project belongs to Hai Anh – Quang Tri Wind Power JSC, located in Lao Bao commune. The plant features 8 wind turbines, each with a capacity of 5MW, totaling 40MW. Notably, the turbine towers stand 125 meters tall with 172-meter rotor diameters, optimizing wind energy capture.

With a total investment exceeding VND 1,500 billion (approximately USD 60 million) across 118 hectares, the plant is expected to supply around 118 GWh of clean electricity annually to Vietnam once fully operational.